VibInfo 发表于 2005-11-17 08:07

混凝土开裂命令流实例


finish
/clear
/title, fixed - fixed concrete beam example
/prep7
et,1,65
mp,ex,1,3e7 ! steel rebar (units are pounds, inches)
mp,ex,2,1e6, ! concrete
mp,dens,2,.00025
tb,concr,2
tbdata,1,.3,.5,200,4000 ! shear coeffs, tensile and compress strength

r,1,1,.03,0,0 ! mat 1 (steel), 3 percent reinforcement in x dir
r,2,1,.01,0,0 ! mat 1 (steel), 1 percent
r,3,1,.04,0,0 ! mat 1 (steel), 4 percent

block,,100,,5,,5
block,,100,5,10,,5
block,,100,10,15,,5
!vovlap,all
NUMMRG,KP, , , ,LOW
numcmp,volu
esize,5
mat,2 ! concrete material
real,1 ! rebar
vmesh,1
real,2
vmesh,2
real,3
vmesh,3

nsel,s,loc,x
d,all,all
nsel,s,loc,x,100
d,all,all
nsel,all
fini

/solu
nsel,s,loc,y,15
sf,all,pres,100
nsel,all
OUTRES,ALL,ALL,
nsub,10
solve
fini

/post1
/DEVICE,VECTOR,1
set,last
plcrack
fini
页: [1]
查看完整版本: 混凝土开裂命令流实例